The Urbanaut® Monorail Technology |
Cost Data | ||||||||||||||||||||||||||||||||||||||||||||||
In This Section Elements of Urbanaut® Project Costs Cost of Type I Single Elevated Guideway Example of Cost of Type I Guideway Cost of Type II Dual Elevated Guideway Cost of Type III Single Guideway at Surface Comparison of Cost with Other Systems (Link)
|
|||||||||||||||||||||||||||||||||||||||||||||||
Cost of any monorail project is quite involved and varies with the location, the geography and the route layout of the monorail guideway, along with the station location and sizes, service and maintenance facilities, switching and total environmental impact on the community. Urbanaut®has the flexibility to integrate future expansion or deletion, which could reduce planning and construction cost. The graphical cost illustration shown in Elements of an Urbanaut®Elevated Monorail Project below is specific to the Urbanaut® technology. While the "Cost Of Depot" is a relatively small item for the Urbanaut®, it is large for the straddle-beam type monorails, which require a very large land area with complicated equipment to move the inseparable massive beam ways with the trains on top.
The "Core System" for the Urbanaut® represents close to 85% of the total project and costs. It embraces: 1. The Civil Works (Elevated Guideway) 2. The Rolling Stock (Vehicles) 3. Signaling (Automatic Control) The "Fixed E&M" (Electrical & Mechanical) integrates and overlaps with the Civil Works The "Movable" (Rolling Stock) includes operational trains and vehicles
The following three cost estimate guidelines for an Elevated Single Guideway, Double Guideway and Guideway at Surface are based upon experience on monorail technology by a number of consultants and contractors. A list of variable costs that may apply to any installation is also provided. Fixed Costs: A. Elevated Guideway,
Including Foundations 42%
= $ 6.30 Mill
Variable cost items to be determined after a preliminary study of the project. Fixed Costs: A. Elevated Guideway, Including Foundations 41.8% = $11.70 Mill B. Passenger Loading / Unloading Facilities (2 Stations) 8.5% = $2.40 Mill C. Maintenance Yards & Operational Control Facility 7.2% = $2.00 Mill D. Electrical Power, Signals, and Moving Block Control 7.2% = $2.00 Mill E. Rolling Stock (3 Single Vehicles or 3 Car Train) 26.8% = $7.50 Mill F. Fees & Contingencies of A, B, C, & D 8.5% = $2.40 Mill Total cost of INTERMEDIATE SIZE PER MILE (1.6 km) 100% = $28.0 Mill
Fixed Costs: A. Excavation, drainage, sub-ballast,
foundation' 22% = $2.00 Mill B. Passenger Loading / Unloading Facilities (2 Stations) 4% = $0.40 Mill C. Maintenance Yards & Operational Control Facility 12% = $1.05 Mill D. Electrical Power, Signals, and Moving Block Control 10% = $0.90 Mill E. Rolling Stock (3 Single Vehicles or 3 Car Train) 42% = $3.75 Mill F. Fees & Contingencies of A, B, C, & D 10% = $0.90 Mill Total cost of INTERMEDIATE SIZE PER MILE (1.6 km) 100% = $9.00 Mill
1. Land acquisition (if necessary public right-of-way not available) 2. Improvements such as relocation of underground and aerial utilities 3. Aerial right-of-way and underground expropriation 4. Parking lots, park-ride facilities 5. Stations built into existing facilities (buildings) 6. Foundations for poor soil conditions and unforeseen underground conditions 7. Special elevated structures that deviate from standard prefabricated designs 8. Legal fees and feasibility studies 9. Unexpected delays and obstructions encountered 10. Financing, interest and loan costs 11. Mobilization costs (Contracts for Design, Engineering, Built proposal)
|
|||||||||||||||||||||||||||||||||||||||||||||||